PROJECTS · 2020
Clean room construction package at ASTI Hanoi Electronics JSC
- Service
- Construction
- Location
- Quang Minh Industrial Park, Me Linh, Hanoi
- Area
- 3000 m²
- Year
- 2020
- Handover
- 2020
The challenge
Hasacon executed this clean room package while Covid was surging — with the schedule critically important. The challenge: keep construction unaffected by the pandemic and hand over on time.
Hasacon's solution
At the 2020 peak, Hasacon's management planned shift rotations with support staff so work continued around the clock, and kept standby replacement personnel ready whenever a worker was affected — protecting the team's health while holding the schedule.
Delivered result
Completed and handed over on schedule thanks to the whole team's effort. The works include compliant electrical, ventilation, lighting and fire-safety systems; the clean room meets every requirement with minimal issues in operation.
Process
- Receive the project and procedures
- Survey the project
- Propose the preliminary plan
- Discuss and approve
- Detailed execution planning
- Prepare workforce & materials
- Build to plan
- Periodic supervision and checks
- Progress reporting
- Complete the work items
- Inspect, assess, accept
- Hand over the project