The challenge

Inside the Sumitomo plant campus, the project created centralised parking for staff — reducing the footprint used for parking and centralising vehicle management — plus warehouse space for post-production recyclable materials and raw material storage, all delivered safely and on schedule.

Hasacon's solution

Hasacon worked with plant management to align requirements and agree a fitting execution plan — protecting safety and the construction schedule.

Delivered result

Delivered a two-storey parking building combined with a warehouse, safe throughout construction. Staff now have spacious covered parking; the two-storey design multiplies capacity, absorbing future growth in vehicle numbers.

Process

  1. Overall site survey
  2. Preliminary data and sketches
  3. Design & simulation
  4. Design suitability review
  5. Design adjustments
  6. Final design approval
  7. Start construction
  8. Execute work items to schedule
  9. Install fire-safety (PCCC) systems
  10. Inspection and acceptance
  11. Handover and final transfer